Q.1 Explain the following a. Rolling wave planning b. Decomposition c. Precedence diagramming method d. Dependency determination


Answer:
a. Rolling wave planning :
This is a technique which plans as and when the project unfolds. In this technique the plans are made with the upcoming events

b. Decomposition  :

This technique is about breaking project work packages into smaller more easily manageable units

c. Precedence diagramming method  :
This is a method for constructing project schedule network diagram that has rectangular boxes, depicting nodes and arrows connecting the boxes, depicting the logical relationship between the activities. this technique is also called Activity on Node (AON).


d. Dependency determination :
This technique is used to define the sequence based on the types of dependencies between the activities 